Fuel Conversion Project
In an effort to control our costs and improve environmental performance, will begin the permitting process to utilize liquefied natural gas to replace Number 2 fuel oil at our Florence facility.
After exploring various energy alternatives we determined that natural gas is the most reliable fuel source and one that would provide us with economic advantage and improve our environmental performance.
The Fuel Conversion Project will comply with local, state and federal permitting requirements. The permitting process is expected to take approximately one year with construction lasting an additional nine months.
Below you will find various documents that will provide insight to the project. We will update this site with project information throughout the permitting and construction process.
Your interest in this project is important to us. If you have questions or comments, please contact us by selecting one of the various options found under the contact us tab.
General Project Information
Media
Permitting
Omya Inc.'s Proposed LNG Facility / Fuel Conversion Project 45-Day Notice of Petition to be filed Under Section 248 at Public Service Board.Omya Inc's submittal letter to submit the Petition and request for a prehearing conference as soon as practicable to initiate the review process.
Omya Inc's Petition requesting the Public Service Board to issue a Certificate of Public Good for the construction and operation of a liquefied natural gas facility at our existing Verpol plant.
- Public Hearing
- Vermont Public Service Board's final order and Certificate of Public Good - November 9, 2012
- Final Engineering Design - In Process
Supporting Documents
Vermont Energy Investment CorporationColby Engineering Company
February 13, 2013
CLF Ventures, Inc.
February 20, 2012